Another major component of our financing plan is a New Markets Tax Credits (NMTC) transaction, which would provide at least $2 millions towards the project. This is a very complex transaction, but we feel confident that the pieces are coming together. A financing task force is assisting in our meetings with banks and organizations to obtain bridge loans and NMTC allocations.
The design team has distributed a bid package, and five contractors have met the qualifications. We will be selecting a general contractor for the building on April 2. We are also finalizing terms with the potential operator of the project.